it takes 20 people 24 days to build a barn. in how many days will the barn be built if they had 32 people working

Respuesta :

bluevortexwitepower bluevortexwitepower
  • 02-02-2019

Answer:

15 days

Step-by-step explanation:

Number of ppl it takes to build a barn in 24 days=20

Time it will take 32 people to build the barn=24*20/32=15 days

Answer Link

Otras preguntas

Find the Slope Using the slope equation
Right triangle abc is on a coordinate plane. segment ab is on the line y = 2 and is 6 units long. point c is on the line x = −3. if the area of δabc is 6 square
please help 10 points!
How do you drown a blonde?
Fahrenheit 451 Question
Determine which set of side measurements could be used to form a right triangle. 3, 11, 20 5, 9, 17 6, 7, 8 6, 8, 10
Mrs. Bowlin organized the glue sticks into 7 bins. How many glue sticks were in each bin? ANSWER QUICKLY PLEASE ANYONE
Please help me with all I will mark you brainly
Find the Slope Using the slope equation
How can this sentence be changed into a simple sentence? The ski club members are raising money for a trip to Aspen, but they will probably pay most of the expe