15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

Enter the value of n so that the expression (-8y + 3) + (2y – 9) is equivalent to (ny – 6).
Question 1 Part A What is a theme of Twelfth Night? A: Family members share a special bond. B: People rarely learn from their mistakes. C: People in love may ac
A student is writing a narrative essay about a surprise party for his grandfather's seventy-fifth birthday. Which lists the best topics to include on a brainsto
5x - 2y = 2 x + 2y = 2
what is the areas of the window shown? use 3.14 for pi. round your answer to the nearest tenth. if you can’t see the pic don’t both answering
Point B, located at (6, 3), is reflected across the y-axis. What are the coordinates of the reflected point? A. (6, 3) B. (-6, -3) C. (6, -3) D. (-6, 3)
A woman drives her car 180 miles in 3 hours. At this rate how far will she travel in 5 hours?
Which two lines here are parallel to one another? (Select 2 equations) a y=x+3 b y=1/3x+2 c y=3x+2 d y=3x-4
What does it mean when a wave is reflected?​
the blue segment below is a diameter of 0. What is the length of the radius of the circle ?