In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

This pedigree supports the fact that the widow's peak is due to a dominant allele, because if it were due to a recessive allele and both parents show the recess
Which types of waves are also called secondary waves
¿Qué efecto tuvo para las arcas fiscales la integración de los territorios ricos en salitre?¿en qué crees que el Estado chileno destino dichos fondos?
What height in meters must the student climb in order to reach the top of the hill?
can someone write 3 sentences or more on this question and choose some words from the word bank to write in the sentences I would appreciate that thanks <3
What was the importance of Rabbi 's for Judaism?​
Solve for w: v = 3p (w -r)​
2. Explain the term risk factors and describe how to reduce your risk of developing two different diseases.
A ________ is an example of a first-line manager.
Help me PLEASEEEEEEEEEEEEE